Local Law 11 (FISP) repairs: Unsafe and SWARMP
A facade report has been filed on your building and it uses two words that decide the next five years: Unsafe and SWARMP. This page is about what each one obliges you to do, how the deadlines actually run, and where the money goes if they slip.
Last updated: November 22, 2026. Written by Zeeshan of Zeetek Construction. We do the repairs, not the inspections.
Everything below is from the Department of Buildings’ own rule, 1 RCNY §103-04, read directly. That matters here more than usual: in researching this page we found a widely shared advisory article telling owners they have 30 days to correct an unsafe condition. The rule says ninety. Check anything you read about this programme, including this, against the rule itself.
This is general guidance, not legal or engineering advice. Your qualified exterior wall inspector and your attorney speak for your specific building.
Does the programme even apply to your building?
The rule covers “all buildings with exterior walls or parts thereof that are greater than six stories, regardless of the information in the Certificate of Occupancy.” That last clause exists because owners have argued from their C of O before, and lost.
There is also a trap that catches buildings nobody counted as tall. Where a building has six stories above grade plane plus a cellar, and “more than half the height of that cellar as measured at any individual exterior wall is above the adjacent ground level, including but not limited to areaways, yards, and ramps”, then all walls of that building become subject to facade inspection. A sloping site or a deep areaway can pull a six-storey building into the programme through a basement wall.
When is my report actually due?
Once per five-year cycle, but the useful detail is that each building has a two-year filing window, and the window is set by the last digit of your block number. You can work out your own from the rule:
| Block number ends in | Two-year filing window |
|---|---|
| 4, 5, 6 or 9 | 21 February of years ending 0 and 5, to 21 February of years ending 2 and 7 |
| 0, 7 or 8 | 21 February of years ending 1 and 6, to 21 February of years ending 3 and 8 |
| 1, 2 or 3 | 21 February of years ending 2 and 7, to 21 February of years ending 4 and 9 |
Three further timing rules catch people out, and all three are about the inspector’s paperwork rather than yours:
- The report must be filed within 60 days of the inspector completing the critical examination.
- It may not be filed more than one year after the close-up inspection, so an old inspection cannot be dusted off to meet a deadline.
- If the Department rejects the report, a revised one is due within 45 days, after which “the original file date will no longer be valid” — which can turn an on-time filing into a late one.
Unsafe: ninety days, and the part that starts immediately
Two separate obligations begin at once, and owners tend to hear only the second.
First, on filing a report of an unsafe condition, the owner “must immediately commence such repairs or reinforcements and any other appropriate measures such as erecting sidewalk sheds, fences, and safety netting as may be required to secure the safety of the public”. Immediately, not within 90 days. Note too that the inspector has a duty of their own: on discovering an unsafe condition the inspector must immediately notify the Department as well as you. The clock is not yours to start.
Second: “All unsafe conditions must be corrected within ninety (90) days from the submission of the critical examination report.” Note the date it runs from — submission of the report, not the date you read it, not the date you got prices.
If the scope genuinely cannot be done in 90 days, that is handled inside the report: the inspector recommends a timeframe, and any later deviation from it has to be notified to the Department with supporting documents. That is a different thing from an extension.
Can I get more time?
Yes — up to a further 90 days at the Commissioner’s discretion. But read what the application has to contain, because this is where most of the avoidable damage on these jobs happens. The application is submitted by the inspector, together with:
- notice that the premises have been secured by shed, fence or other measures;
- “a copy of the contract indicating scope of work to remedy unsafe conditions”;
- the inspector’s estimate of the time the repairs need;
- a statement of all applicable permit requirements;
- a notarised affidavit by the owner that the work will be completed within that estimate;
- a fee.
So you cannot apply for an extension until you have a contractor under contract. The contract is a required attachment. An owner who spends day 60 to day 85 collecting bids has not just lost the repair time; they have lost the ability to ask for more of it, because the application cannot be assembled without the thing they have not yet signed.
And the rule closes the obvious door twice, in identical words in both the first and the further extension provisions: “Financial considerations shall not be accepted as a reason for granting an extension.” Waiting for a reserve study, a special assessment or a loan is not a reason the Department will accept. A further extension beyond that needs an unforeseen delay such as weather or a labour strike, unforeseen circumstances such as fire or collapse, a hazard whose nature genuinely needs longer, or progress photographs.
The practical reading: start getting written scopes while the report is still in draft with your inspector. It costs nothing and it preserves an option you otherwise lose by default.
How the penalties escalate, with the shed in the arithmetic
The headline numbers are flat and widely quoted. Failure to file an acceptable report is $5,000 per year immediately after the filing window ends. Late filing adds $1,000 per month on top, from the day after the deadline until an acceptable report is filed.
The one almost nobody shows an owner is the penalty for an uncorrected unsafe condition, which is not flat. It grows with the length of your sidewalk shed, every month:
| Base penalty | Plus | |
|---|---|---|
| Year 1 | $1,000/month | — |
| Year 2 | $1,000/month | $10 per linear foot of shed, per month |
| Year 3 | $1,000/month | $20 per linear foot, per month |
| Year 4 | $1,000/month | $30 per linear foot, per month |
| Year 5 | $1,000/month | $40 per linear foot, per month |
Put a number on it. A 60-foot shed on a modest building, in year three of an uncorrected condition, is $1,000 plus 60 × $20, so $2,200 a month in penalties alone — before the shed rental, and before whatever the dark storefront underneath it is costing a commercial tenant. In year five the same shed is $3,400 a month and rising.
Note also when the meter stops. The penalty runs until the Department receives an acceptable amended report and “the sidewalk shed has been removed and the associated permits are signed off with the Department, including shed permits”, or an extension is granted. Leaving the shed up after the repair is finished, because nobody chased the sign-off, keeps the charge running on work that is already done.
SWARMP is not a synonym for later
SWARMP means safe with a repair and maintenance program: not dangerous today, but it will be. It is widely treated as the category you can ignore for five years. The rule does not support that reading, in three separate ways.
The deadline is the inspector’s, not the cycle’s. The owner is responsible for ensuring SWARMP conditions are corrected “within the time frame recommended by the QEWI, and are not left to deteriorate into unsafe conditions”, and for notifying the Department of any deviation from that timeframe. If your report gives a condition eighteen months, eighteen months is the deadline.
You cannot call the same thing SWARMP twice. “A report may not be filed describing the same condition and pertaining to the same location on the building as SWARMP for two consecutive report filing cycles.” The deferral is available once.
Your next inspector is obliged to escalate it. The inspector must certify the correction of each condition reported as requiring repair in the previous cycle, and must “report conditions that were reported as SWARMP in the previous report filing cycle as unsafe if not corrected at the time of the current inspection”. That is not a judgement call they make building by building; it is what the rule tells them to do. The same provision also requires them to report a previous repair as unsafe if it needs doing again — which is a quiet argument for having the first repair done properly.
And there is a specific charge for the sequence: an owner who fails to correct a SWARMP condition from the previous cycle and then files it as unsafe is liable for a civil penalty of $2,000 — on top of the unsafe-condition penalties above, and the shed the escalation now requires.
So the real choice on a SWARMP item is between a planned repair at your own pace, with no protection and no deadline pressure, and the same repair later under a shed with a meter running. That is a budgeting question, and it is much easier to answer with a written scope in hand. Our facade restoration page covers what the repairs themselves involve.
Getting the shed down again
Within two weeks of the repairs being finished the inspector re-inspects and files a detailed amended report stating the building’s revised status, and you obtain the permit sign-offs. If that amended report is rejected there are 45 days to file a revised one, and after two rejections a new filing fee is due.
Sheds and other protective measures “must remain in place until an amended report is accepted”. There is, however, an earlier route that is worth knowing: the inspector “may request permission for the removal of the shed upon submission of a signed and sealed statement certifying that an inspection was conducted, the conditions were corrected and the shed is no longer required”, and permission may be granted in the Commissioner’s sole discretion. Given what the shed costs in penalties and rent, that request is usually worth making rather than waiting for the full amended report to clear.
Was my inspection a real inspection?
This is worth checking before you accept a long list of conditions, and it is one of the few parts of the programme with hard numbers you can hold a report against.
Close-up physical examinations — from scaffolding or another observation platform — “must be performed at intervals of not more than 60'-0"”, and the rule sets a minimum count against the length of each elevation fronting a public right of way:
| Length of elevation | Minimum close-up examinations |
|---|---|
| Under 60 ft | 1 |
| 60 to under 120 ft | 2 |
| 120 to under 180 ft | 3 |
| 180 to under 240 ft | 4 |
| 240 to under 300 ft | 5 |
| 300 to under 360 ft | 6 |
| each further 60 ft | one more |
Those examinations must run “along a path from grade to top of an exterior wall fronting each public right-of-way, using at least one scaffold drop or other observation platform configuration, including all exterior wall setbacks”, and the inspector is to choose the most deleterious locations rather than the most convenient ones.
And the sentence to keep for the next sales call: “The use of drones, high resolution photography, non-destructive testing, or other similar methods does not eliminate the requirements for close-up inspections.” Drone survey is a useful addition. It is not a substitute, and a cheap inspection that skipped the drops is a report you may have to pay for twice.
Where we fit, and where we do not
The programme deliberately separates the person who decides what is wrong from the person who fixes it. The inspection and the report belong to a qualified exterior wall inspector, an engineer or architect. We are not that, and we do not file reports, extensions or sign-offs. We are the contractor who carries out the repairs the report calls for, and who gives your inspector something to certify.
What is useful to ask of a repair contractor on a FISP job is narrower than people expect: a written scope tied to the numbered conditions in your report, a realistic programme for getting the protection down rather than only for finishing the masonry, and an estimate that names what is excluded. Every estimate is an itemised written scope of work, with exclusions stated on every job, and if an extension application is likely, the contract your inspector needs to attach is the document we are signing anyway.
Most conditions on these reports come down to joints, and that is pointing work. Rusting steel over windows is lintel work. Parapets, coping and the top of the wall weather on several faces and show up on these reports more than anything else — and a street-facing parapet carries a separate annual duty of its own, whatever the facade cycle says. That is the Local Law 126 parapet observation, and it applies at any height.
Send us the report
If you have the report as a PDF, send it. We will come back on the conditions listed, which of them drive the protection, and what the sequence should be to get the shed down soonest. Call (929) 412-6597 or use the estimate form.